Flange Bolt tightening Procedure/Bolt Tightening Steps

The correct placement of gasket and proper tightening of bolts in a flanged joint will ensure a leak-free joint. Proper bolt tightening will ensure uniform load distribution in all bolts without damaging the gaskets. The following procedure describes how to tighten flange bolts.

Flange Bolting Procedure

Before actual tightening starts, the flange, gasket, bolts/nuts need to be observed as below:

Flange checking points before flange bolt up

Leakage through a flanged joint is prevented as gasket material flows inside the flange surface imperfections and seal them. But there are limitations that a gasket can successfully seal. Hence, Flange surfaces must be checked thoroughly to ensure the absence of large nicks, dents, or gouges. So the flange surface finish must be as per manufacturer recommendation for particular gasket materials. Recommended values of flange surface roughness are as follows:

  • Solid Metal Gaskets: 63-80 rms
  • Spiral Wound Gaskets: 125-250 rms
  • Jacketed or Metal Clad Gaskets: 63-80 rms

Here, rms stands for root mean square. Roughness is normally specified in millionths of an inch as the average of the peaks and valleys measured from a midline of the flange surface.
A flange is recommended to be machined using a 1/16″ radius, round-nosed tool to have 30-55 serrations per inch in a concentric or spiral pattern.

Bolted Flanged Joints at operating plant
Fig. 1: Bolted Flanged Joints at operating plant

Check the following points prior to flange bolting.

  • Before inserting the gasket in between the pipe flanges, check the flanges are parallel and co-axial (When none of the bolts is installed in the flange).
  • As per ANSI B 31.3 clause no. 335-C, permitted tolerances are as follows: Flange faces shall be aligned to the design plane within 1 mm in 200 mm(1/16 in. /ft) measured across any diameter; flange bolts holes shall be aligned within 3 mm (1/8 inch) maximum offset.
  • If pipe flanges are not meeting the ANSI B31.3 requirement, the piping shall be rectified.
  • All gasket seating areas shall be cleaned properly before gasket insertion. If serration is damaged, re-serration must be done.

Checkpoints for Gasket prior to tightening flange bolts

  • Ensure the gasket of the correct dimension and of specified material is used.
  • The gasket shall be located correctly to ensure full sealing as indicated in the drawing. For example – a gasket on the tube-sheet of an exchanger needs to be located so that the outer periphery of gasket matches with OD of tube-sheet at all points.
  • Examine the gasket in advance and ensure that it is free from defects.

Bolts for Pipe Flanges

Bolts create the compressive pressure on the flanges and gasket so that leakage is prevented. So, while selecting, the temperature variations in service must be considered. Recommended values of flange bolting temperature are as under.

Recommended Bolt Temperatures with respect to materials
Fig. 2: Recommended Bolt Temperatures with respect to materials
  • Ensure that material of all bolts and nuts is as specified.
  • Bolts & nuts shall be cleaned with suitable solvents like Diesel / CTC using a wire brush, especially in the threaded portion.
  • The bolt shall be lubricated with molybdenum disulfide and it is essential especially in all bolts of size 7/8” and above to check the application as the bolt load developed by torque is dependent on the lubrication of threads.
  • It is recommended to avoid the use of short bolts on the flange joints.

Flange Tightening Procedure

  • It is important that all bolted joints are tightened uniformly and in a diametrically staggered pattern (A typical sketch attached in Fig. 3).
Typical sketch showing bolt tightening pattern.
Fig. 3: Typical sketch showing bolt tightening pattern.
  • In case of pipe flanges 8″ NB & up to 12″NB and having a pipe with spacer piece and a minimum of two gaskets (which are getting compressed simultaneously during tightening) the distance between two flanges should be measured at four locations like 12’o clock, 3’o clock’ 6’o clock and 9’on clock positions and maintained equal for even tightening. The tightening shall be gradual and uniform. In case of flanges above 12” NB distance between the flanges shall be measured in 8 locations for uniform tightening.
  • All stud bolts of 7/8″ and above shall be tightened using a torque wrench. While tightening the bolt with torque wrenches (for pipe / Manway flanges) ensure that tightening load to each bolt is applied as uniformly as possible. The tightening shall be carried out in three or four stages in steps of 30, 50 & 70 percent of the final torque value. A fourth stage again uses 70 percent of the final torque value.
  • For heat exchangers flanges torque values to be 30,70,100 and 100 percent of the final torque value.
  • Where recommended using hydraulic tensioner for bolt tightening follow the manufacturer recommendations.

A table is provided in Fig. 4 below to show an example of torques applied for bolt tightening.

Suggested Applied Torque for ANSI 150 lb Flanges
Fig. 4: Suggested Applied Torque for ANSI 150 lb Flanges

Wrong Practices followed for Flange Bolt-Tightening

Many a time, plant operators use wrong practices while flange bolt tightening as follows

  • Improper sequence of bolt tightening.
  • Reuse of old gasket.
  • Procurement of un-specified material.
  • Improper storage of gaskets.
  • Use of many gaskets to fill a large gap between flanges.
  • Use of ordinary fasteners instead of high tensile fastener
  • Use of dirty / rusted fasteners without lubrication.

Few more related articles.

How to Select a Bolt: A definite Guide
Bolting Features in Bolted Connections/Bolted Joints
Guide for Coating Selection for External Bolting to Reduce Corrosion
Collar Bolts To Maintain Removable Bundles in Heat Exchangers

Print Friendly, PDF & Email

Anup Kumar Dey

I am a Mechanical Engineer turned into a Piping Engineer. Currently, I work in a reputed MNC as a Senior Piping Stress Engineer. I am very much passionate about blogging and always tried to do unique things. This website is my first venture into the world of blogging with the aim of connecting with other piping engineers around the world.

Leave a Reply

Your email address will not be published. Required fields are marked *

Recent Content

Enable Notifications    Ok No thanks